Specification |
For 25 Cum/Hr Acetylene Plant |
For 50 Cum/hr Acetylene Plant |
For 100 cum/hr Acetylene Plant |
|
Capacity |
For 25 Cum/hr |
50 cu.m/Hr |
100/Hr |
|
Cylinders filled per batch |
30 |
60 cylinders |
120 cylinders |
|
Carbide size |
4-25mm |
4-25 mm (or higher) |
4-25mm (or Higher) |
|
Hopper Capacity |
100 Kg |
150 kg |
300 kg |
|
Carbide required per batch |
600 kg approx.(depending on carbide quality) |
1,200 kg approx.(depending on carbide quality) |
2700 kg approx. (depending on carbide quality) |
|
Water required |
10 liters per kg of Calcium Carbide used |
10 liters per kg of Calcium Carbide used |
10 liters per kg of Calcium Carbide used |
|
Power required |
12kw |
18 KW |
30 KW |
|
Start up time |
15 minutes |
15 minutes |
15 minutes |
|
II S/BS. Specifications conforms to |
IS 8471-1977 IS 2148 (Group II-B)-1968 As amended |
IS 8471-1977 IS 2148 (Group II-B)-1968 As amended |
IS 8471-1977 IS 8471-1977 IS 2148 (Group IIB-1968 as amended) |
|
Space Requirement |
70 Sq.M. |
110 Sq.M |
150 Sq.M |
|
2. Carbide Storage Area |
75 Sq.M. |
112 Sq.M |
175 Sq.M. |
|
3. Cylinders filling Area |
40 Sq.M. |
60 Sq.M |
100 Sq.M. |
|
4. Cylinders storage area (depending upon cylinders inventory) |
100 Sq.M. |
160 Sq.M |
200 Sq.M. |
|
5. Lime slurry disposal area |
100 Sq.M. |
180 Sq.M |
250 Sq.M. |
|
6. Free space around the plant (on all sides) |
16 M |
18.5 M |
20 M |
|
7. Acetone godown |
12 Sq.M. |
20 Sq.M |
30 Sq.M. |